Some Achievements

CEB Kits – Mauritius
  • Scope: EPC for installations of 1149 PV Grid tied Kits (2MWp)
  • Installation Time: 7 months
Djema 1 – Mayotte
  • Installed Capcity: 0.9 MW + 1 MWp Energy Storage
  • Annual Energy production: 1440 MWp
  • Construction Time: 7 months
SPV Petite Rivière – Mauritius
  • Installed Capcity: 5 MWp
  • Annual Energy production: 8250 MWp
  • Construction Time: 8 Months
Dzoumogne – Mayotte
  • Installed Capacity: 1.8 MWp & 2MWp Energy Storage
  • Construction Time: 8 months
Henrietta – Mauritius
  • Annual Energy production: 3 000 MWp
  • Construction Time: 8 months
Montvendre – France
  • Installed Capcity: 2 607 kWp
  • Annual Energy production: 3 310 MWp
  • Construction Time: 8 Months
12 CWA sites
  • Installed Capacity: 250 kWp
  • Construction Time: 8 Months
CEB 1MW Grenade Rodrigues
  • Installed Capacity: 1MW
  • Construction Time: 8 Months

Interested In What We Do?